What Do Data Centers Mean for Stafford County, VA?
Reported by Barbara Jennings, REALTOR, eXp Realty. Every project count, square footage figure, vote, and date below is drawn from the dated reporting and official county sources listed in the Sources section. No figures other than those published are cited.
Data centers are becoming a defining feature of Stafford County's growth. As of early 2026 reporting, the county had about 18 data center projects in the pipeline, with three projects totaling more than 7 million square feet already under construction; by mid-2026 the county reported 16 projects in the pipeline, five approved (three under construction) and 11 still under review. Data centers bring large commercial tax revenue that can support schools and county services, and they also raise real questions about power demand, water, traffic, and neighborhood character. This article lays out what is proposed, what has been decided, and what residents can expect next, sourced from dated county and news reporting.
Data centers are the large industrial buildings that store the computer servers behind cloud computing, streaming, and artificial intelligence. Stafford County sits just south of Northern Virginia's "Data Center Alley," and developers are moving into the county along the I-95 corridor, near Stafford Regional Airport, and along Kings Highway. I'm Barbara Jennings, a REALTOR with eXp Realty who has served the Fredericksburg region for more than 20 years, and I track these proposals because they show up in buyer questions, county budgets, and the way neighborhoods change. Here is a balanced, fact-based picture of what data centers mean for Stafford County, with every number sourced.
Latest update: November 23, 2026
The two county decisions this site has been tracking are on the record. On November 18-19, 2026, the Stafford County Planning Commission voted 4-3 on each measure to recommend denial of all four Kings Highway (Route 3) data center applications, Forest Lane, Simms Farm, Sisson North, and Sisson South, which together form the proposed Kings Corridor Technology Campus. The meeting ran nearly 11 hours, into the early hours of Thursday, November 19, with more than 100 residents testifying in opposition, and the recommendation covers the conditional use permits, the rezoning of roughly 1,400 acres from agricultural to heavy industrial for 37 data center buildings and 14 electrical substations, and the comprehensive plan amendments. FOX 5 DC, the Richmond Times-Dispatch, and the Fredericksburg Free Press all reported the recommendation to deny on November 19, 2026. The four applications now move to the Stafford County Board of Supervisors for a final decision.
A day earlier, on Tuesday, November 17, 2026, the Spotsylvania County Board of Supervisors voted 4-3 to approve the special use permit for the Crossroads Technology Campus, the roughly 555-acre data center in the Lee Hill District near Benchmark Road and U.S. 17. The approval carried more than 50 conditions covering noise mitigation, generator emissions standards, setbacks, and a ban on using groundwater for cooling, and the developer projects about $30 million in annual tax revenue; the project still needs site-plan and other permits before construction. I covered both decisions in What the Latest Data Center News Means for Fredericksburg, Stafford & Spotsylvania Homeowners.
Both outcomes leave the biggest chapter open: the Stafford Board of Supervisors now weighs the Kings Corridor recommendation to deny, and no vote date had been set as of this update. County staff had recommended denying the vast majority of the four applications over water, wells, and lighting concerns, and the Planning Commission's 4-3 recommendation to deny aligns with that guidance.
Latest update: November 16, 2026
Two county decisions were then on the near-term calendar. On Wednesday, November 18, 2026 at 6 p.m., the Planning Commission held a single combined public hearing on the four Kings Highway (Route 3) data center proposals, Forest Lane, Sisson North, Sisson South, and Simms Farm, which together span roughly 1,400 to 1,500 acres and could hold up to 37 data center buildings and 14 substations. FXBG Advance reported on November 9, 2026 that the applicant was presenting the four projects as an "all or none" package, while county staff had recommended denial of the vast majority of the applications over water, wells, and lighting concerns. The hearing was moved from October 14 by agreement of the applicant and staff.
A new proposal entered the pipeline this fall: the Enon Road Tech Park rezoning in the Hartwood District, a request to rezone roughly 160 acres at Enon Road and Wyatt Lane from agricultural and light-industrial to heavy industrial for up to about 2 million square feet of data center uses. The resident group Save Stafford, which tracks county decisions, lists the application as in review with a public hearing and Board of Supervisors decision still pending.
Two pipeline facts from the county's own materials round out the picture: the Stafford Technology Campus (roughly 539 acres, 5.8 million square feet) is under construction, and a second proposed campus, GWV Data Centers (roughly 1,042 acres, about 7.9 million square feet), remains under review. On September 1, 2026, the Board of Supervisors directed staff to draft letters asking the governor to consider a special session on data center rules and to weigh a temporary pause on new large-scale approvals; no moratorium has been adopted.
1. How big is Stafford's data center pipeline?
In a March 2026 report, Virginia Business reported that Stafford had about 18 data center projects in the pipeline, with three projects totaling more than 7 million square feet under construction in the county. The jump was striking in a county whose economic development director had predicted at the start of 2025 that data centers could go from zero to "a lot" within three years.
By mid-2026 the picture had sharpened. Potomac Local News reported on July 2, 2026, after a June 23 Board of Supervisors work session, that the county was processing 16 data center projects: five approved (three of them under construction) and 11 still under review. County officials also said a moratorium on new proposals was not legally feasible, so the pipeline continues under current rules while state lawmakers debate industry incentives.
2. Which data center sites are approved in Stafford County?
Stafford County's official Planning and Zoning data centers page currently lists these approved sites:
- Stafford Technology Campus: 5,800,000 square feet, 20 buildings
- Old Potomac Church / Potomac Church Tech Center: 478,310 square feet, 2 buildings
- Centreport Gateway: 730,000 square feet, 3 buildings
- Vantage VA-4 / Melrod: 926,800 square feet
The county page is the source for these figures, and it is the place to check for the official, current list as approvals change.
3. What is Vantage Data Centers building on Centreport Parkway?
One of the largest single commitments is Vantage Data Centers' $2.2 billion, three-building campus on Centreport Parkway, a fast-growing industrial hub along Interstate 95 near Stafford Regional Airport. According to Virginia Business, the campus is among the projects under construction, and its first building is expected to deliver in 2026. The company announced the project in November 2025, and the campus is expected to add significant annual property tax revenue to the county.
4. What did the Planning Commission recommend in August 2026?
In late August 2026, 7News WJLA reported that the Stafford County Planning Commission voted 4-3 to recommend the Board of Supervisors approve a proposed 590,000-square-foot data center complex located between I-95 and Route 1 in the Falmouth District. The project, proposed by Falmouth Tech LLC, calls for two two-story data center buildings totaling 590,000 square feet plus an electrical substation on about 121 acres near the Rappahannock Regional Jail, scaled back from an earlier three-building design. The vote came amid visible resident opposition and ongoing debate over how fast data center growth should move in the county.
5. What is the Kings Corridor Technology Campus, and why are neighbors opposed?
The most contested proposals are the Kings Corridor Technology Campus sites along Kings Highway (Route 3) near the Rappahannock River. In October 2026 reporting, 7News WJLA described a proposed four-site data center complex spanning more than 1,500 acres of farmland and forest along Route 3, with homes adjacent to all four locations (the applications are known as Forest Lane, Sisson North, Sisson South, and Simms Farm).
Residents told WJLA they worry about the river, private wells, wildlife, traffic, and the character of their neighborhoods, with one homeowner describing the scale of the buildings looming over a home. The developer's attorney told WJLA that at full buildout, Kings Corridor is projected to generate $245 million annually for the county, just over 20 percent of Stafford's total budget, money the developer says would support school funding and other county services.
County staff released their reports on October 9, 2026 recommending denial of the vast majority of the four applications over water, wells, and lighting concerns. The public hearing originally set for October 14, 2026 was postponed by agreement of the applicant and staff and rescheduled to Wednesday, November 18, 2026 at 6 p.m. as a single combined hearing covering all four projects at once. FXBG Advance reported on November 9, 2026 that the applicant was presenting the four applications as an "all or none" package. On November 18-19, 2026, the Planning Commission voted 4-3 on each measure to recommend denial of all four applications after a nearly 11-hour meeting in which more than 100 residents spoke in opposition, moving the decision to the Board of Supervisors. I wrote a fuller update on the region's data center news, including the Kings Corridor staff recommendation, in What the Latest Data Center News Means for Fredericksburg, Stafford & Spotsylvania Homeowners.
6. What is happening with data centers in neighboring Spotsylvania County?
Data centers are an equally big topic just south of Stafford. Through mid-2026, Spotsylvania County had seen 21 data center permit filings across three operators: Amazon Web Services, PowerHouse Data Centers, and RCK Digital. The largest project is PowerHouse 95, an 800-megawatt hyperscale campus under construction along the I-95 corridor. Another notable approval is Hunter's Ridge South near Lee's Hill, a roughly 2.2 million-square-foot campus approved by the Board of Supervisors in August 2025.
Spotsylvania has also tightened its rules faster than most counties, and the sequence is worth knowing because it shows what local control looks like in practice: a code amendment permanently bans the use of potable water for industrial cooling; a December 2025 code amendment limited by-right data center development and adopted design standards; a February 2026 amendment eliminated by-right data center development entirely and required a special use permit in office, commercial, and industrial districts; and the county adopted guidelines calling for a minimum 300-foot restricted buffer along property lines adjacent to residential uses, schools, parks, places of worship, and the Rappahannock River. For the homeowner perspective, see Data Centers Are Coming to Spotsylvania: Here's What It Means for Homeowners.
7. What else is in Stafford's data center pipeline?
Beyond the approved sites and the Kings Corridor applications, three items are worth tracking. The Enon Road Tech Park rezoning in the Hartwood District asks the county to rezone roughly 160 acres at Enon Road and Wyatt Lane from agricultural and light-industrial to heavy industrial for up to about 2 million square feet of data center uses and related infrastructure; the application is in review with a public hearing and Board decision still pending, according to Save Stafford.
The Stafford Technology Campus, roughly 539 acres and 5.8 million square feet, is under construction, and a second proposed campus, GWV Data Centers at roughly 1,042 acres and about 7.9 million square feet, remains under review. On the policy side, the Board of Supervisors on September 1, 2026 directed staff to draft letters asking the governor to consider a special session on data center rules and to weigh a temporary pause on new large-scale approvals. No pause has been adopted, and county officials have said a moratorium on new proposals is not legally feasible under current rules, so the pipeline continues to move through the existing process.
The economic case and the community concerns
The economic arguments: data centers are among the largest commercial taxpayers in Virginia, and county officials point to the revenue they bring to schools, roads, and public safety without the same daytime population and classroom pressure as residential development. Stafford's own forecasting work anticipates the buildout of approved sites to contribute meaningfully to the county's budget over time, and the Kings Corridor developer's $245 million annual projection illustrates how large that revenue could be at full buildout.
The community concerns: data centers are power-hungry. They draw large amounts of electricity, need water or air for cooling, generate noise and traffic during construction and operation, and can change the character of the rural corridors where they are proposed. In Stafford, residents near the Rappahannock River have raised the most pointed questions about wells, the river, and neighborhoods, and groups such as Protect Stafford have pushed for tighter setbacks and buffers. These are legitimate questions, and the county's public process is where they get weighed.
Neither side of this debate is settled, and this article makes no claim about what data centers will do to any specific home's value. What is clear is that the decisions being made now, project by project and hearing by hearing, will shape Stafford for decades. I covered the buyer and seller side of this conversation in Are Data Centers Changing Stafford VA Real Estate?
What this means for homeowners
If you live in or are buying in Stafford, the practical takeaway is to know what is proposed near the property you own or are considering. The county publishes current data center information on its Planning and Zoning pages, including the approved sites list and the Kings Highway (Route 3) materials. The November 18-19, 2026 hearing was a direct way residents weighed in, and the four Kings Corridor applications now await a final decision by the Board of Supervisors, so that is the next date to watch. Ask where power lines and substations sit, how cooling water will be sourced, what traffic is expected, and which parts of a proposal are already approved versus still being debated.
Buying or selling in Stafford County?
Call or text Barbara Jennings at 540-840-1133 or book a conversation online.
Book a Conversation with BarbaraSources
- Virginia Business: "NoVa data center development moves down I-95" (March 2026): approximately 18 Stafford projects in the pipeline, three under construction totaling more than 7 million square feet, and the Vantage $2.2 billion Centreport Parkway campus.
- Potomac Local News (July 2, 2026): 16 Stafford data center projects in the pipeline: five approved, three under construction, 11 under review.
- Stafford County Planning and Zoning: Data Centers page: approved site list, square footage, and building counts.
- 7News WJLA (August 2026): Planning Commission 4-3 vote recommending the 590,000-square-foot complex between I-95 and Route 1.
- 7News WJLA (October 9, 2026): Kings Corridor proposals, resident opposition, and the developer's $245 million annual projection.
- 7News WJLA (October 14, 2026): Kings Corridor hearing postponed and rescheduled to November 18, 2026, after county staff urged denial.
- Stafford County: Data Centers Along Kings Highway (State Route 3): November 18, 2026 rescheduled public hearing.
- Spotsylvania County: Data Center FAQs: permit filings, PowerHouse 95, Hunter's Ridge South, and the potable water, by-right, and special use permit rules.
- Spotsylvania County: Guidelines for Data Center Development, adopted February 24, 2026: the 300-foot restricted buffer guidelines.
- FXBG Advance (November 9, 2026): Kings Corridor "all or none" package, the four application names, the 48-building and 14-substation scale, and the November 18 combined hearing.
- Save Stafford: Enon Road Tech Park: the roughly 160-acre Hartwood District rezoning request and its review status.
- FOX 5 DC (November 19, 2026): Stafford Planning Commission 4-3 recommendation to deny the four Kings Highway data center applications.
- Richmond Times-Dispatch (November 19, 2026): recommendation to deny the massive Stafford data center proposal.
- Fredericksburg Free Press (November 19, 2026): Stafford Planning Commission recommends against the large data center project, with the acreage, building, and substation counts and the 11-hour hearing.
- Fredericksburg Free Press (November 18, 2026): Spotsylvania Board of Supervisors 4-3 approval of the Crossroads Technology Campus special use permit with more than 50 conditions.
Project counts, square footage, votes, dates, and revenue figures are as published by the sources above as of the date of publication. Information deemed reliable but not guaranteed and should be independently verified. This article is for educational and informational purposes only and does not constitute professional or financial advice.
Preferred Lenders
Financing is the other half of every home purchase, and I work with lenders who know the Stafford and Fredericksburg market. My two trusted mortgage partners, both with Guaranteed Rate, help area buyers explore loan programs, down payments, and monthly payments based on their individual situation.
Trusted local mortgage guidance for Stafford-area buyers, from rates to a smooth close.
Clear, responsive mortgage help for buyers financing a home in Stafford and nearby counties.
Learn more about both lenders on my preferred lenders page. A pre-approval letter tells you what you can afford and makes your offer stronger in any negotiation.
Barbara is a REALTOR with eXp Realty, licensed in Virginia (0225179074), serving Fredericksburg, Stafford, Spotsylvania and surrounding counties. For the region-wide view, see the Fredericksburg area market report, or start with the Living in Stafford, VA guide for schools, commutes, and neighborhoods. Request a free home valuation anytime, or reach Barbara directly at (540) 840-1133.
Barbara Jennings, REALTOR, eXp Realty. Virginia Real Estate License #0225179074 · 800 Corporate Dr. Suite 301, Stafford, VA 22554 · (866) 825-7169. Equal Housing Opportunity. We are committed to compliance with all federal, state, and local fair housing laws and do not discriminate against any person because of race, color, religion, sex, national origin, familial status, disability, or any other protected class. Each office is independently owned and operated. Information deemed reliable but not guaranteed. Not responsible for typographical errors. Square footage is approximate and should be independently verified. All listing information is provided by Bright MLS and should be verified by the user.
Disclaimer: General real estate information only. This article does not predict or guarantee property value outcomes, tax outcomes, or project approvals. Financing qualifications, contract terms and transaction timelines vary. Consult the appropriate licensed professionals before making financial or legal decisions.